cdub
Posts: 1073
Joined: Sun Aug 15, 2010 9:58 pm
Delivery Date: 26 Jun 2015
Location: La Crescenta, CA

Re: EV Project/Blink Installs

Thu Apr 14, 2011 12:39 pm

Just got a call from the contractor that was going to do my EV Project Blink install on Tuesday. Apparently GWP is now requiring second meters for EV chargers?

This rule just came down. Insane. I'm a little mad right now.

Needless to say my install has been postponed.
La Crescenta, CA
Nissan LEAF™ ETEC trim, Cayenne Red
Reserved: 4/20
Ordered: 10/16 (Sept. order)
Delivered: 6/2 (4-22er)

VIN: 2106

solardude
Posts: 109
Joined: Mon Apr 12, 2010 11:11 pm
Delivery Date: 26 Jun 2015
Location: Corvallis, Oregon

Re: EV Project/Blink Installs

Wed May 04, 2011 10:23 pm

Got my Blink charging station installed today. I believe it is a rather unique install, so i am providing a link to my Flickr pics (2). I have a carport in which the supports are 4' from the side of the house. I had the installer put the charging station on the house, but wanted to mount the cord reel on one of the carport supports. i had an black acrylic mounting plate fabricated locally. the plate is 18" round on one side and 18" square on the opposite, mounting side. slightly over sized U bolts were used at a 60 degree angle to secure the plate to the support. the installer let me mount the cord reel while he worked on the charging station. i think it all came out pretty slick. now if only they would deliver my car (dash says July).

http://www.flickr.com/photos/johnnycee/ ... 6650831914

cdub
Posts: 1073
Joined: Sun Aug 15, 2010 9:58 pm
Delivery Date: 26 Jun 2015
Location: La Crescenta, CA

Re: EV Project/Blink Installs

Wed May 04, 2011 10:44 pm

Getting mine installed tomorrow. Wish me luck. :) Hope there aren't any surprises like "hey this costs much more than we thought"
La Crescenta, CA
Nissan LEAF™ ETEC trim, Cayenne Red
Reserved: 4/20
Ordered: 10/16 (Sept. order)
Delivered: 6/2 (4-22er)

VIN: 2106

User avatar
walterbays
Forum Supporter
Posts: 1209
Joined: Wed Sep 01, 2010 2:41 pm
Delivery Date: 26 Jun 2015
Location: San Diego, CA

Re: EV Project/Blink Installs

Wed May 04, 2011 10:54 pm

My Blink installation was just done by Sunwest Electric, with second meter at my request. They were on schedule and on time, courteous and professional. They did a neat, quick, and careful job, with no surprises, and no charge. No money, that is; it came within the EV Project limits. As for an electric charge, that awaits city inspection, SDG&E meter hookup, and of course a car.

LEAFfan
Posts: 4828
Joined: Fri Apr 23, 2010 6:08 pm
Delivery Date: 08 Jun 2011
Leaf Number: 1855
Location: Phoenix Area

Re: EV Project/Blink Installs

Wed May 04, 2011 11:49 pm

I had mine done a week ago Monday by Interstates. Jason & Manny did a really good, fast, nice, clean job. There is no conduit showing on the inside of the garage (they went down the wall in the attic) and made the receptacle flush with the wall.
2013 LEAF SV Del. 2/28/13
2013 LEAF World Record for Most Miles Driven On One Charge-188 miles/8.8 m/kW h
4.8 kW DC PV ($ .91/W fully installed)/ Dec., 2010

User avatar
sdbonez
Posts: 468
Joined: Tue Sep 28, 2010 11:44 pm
Delivery Date: 26 Jun 2015
Location: San Diego, Ca (San Marcos)

Re: EV Project/Blink Installs

Wed May 04, 2011 11:56 pm

walterbays wrote:My Blink installation was just done by Sunwest Electric, with second meter at my request. They were on schedule and on time, courteous and professional. They did a neat, quick, and careful job, with no surprises, and no charge. No money, that is; it came within the EV Project limits. As for an electric charge, that awaits city inspection, SDG&E meter hookup, and of course a car.
Make sure Sunwest is moving quickly on your inspection...sometimes, they need a friendly reminder :)
EV Prj: prereg 4/19 11:21a, appvd 7/22 11:34a, on-site eval 8/27 1pm, installed 3/30
Leaf: Red eTec resvd 4/20 2:33p, order open 8/31 11:30a, confirmed 9/3 2:00p, Carwings 3/9
Dash@Delivery 4/8, 7-day on 3/23, Delivered 03/30, Carwings: 'Bonez' VIN#728

GroundLoop
Posts: 1725
Joined: Mon Sep 13, 2010 9:31 pm

Re: EV Project/Blink Installs

Thu May 05, 2011 12:00 am

So far, very happy with Sunwest's work here. Very neat and tidy.. expert sealed holes through stucco, nice conduit bends, answered all questions, and accommodated my request to hug the ceiling. Completed on-time, no hassle.

Now I wait for inspection and meter.

User avatar
ttweed
Posts: 1089
Joined: Tue Sep 07, 2010 8:31 am
Delivery Date: 01 Apr 2011
Leaf Number: 1317
Location: La Jolla, CA
Contact: Website

Re: EV Project/Blink Installs

Thu May 05, 2011 6:06 am

sdbonez wrote:Make sure Sunwest is moving quickly on your inspection...sometimes, they need a friendly reminder :)
I concur. My install went quickly and smoothly, once I got it scheduled, which took a "reminder" email to accomplish (two weeks after the car was delivered). Then a week went by with no inspection, so I sent another email to Shawn at Sunwest asking if this was normal. No reply, so after another week I sent a second email. Received an apology the next day with an explanation that my electrician had been "called away with a family emergency." The inspection was scheduled the next day, and Shawn emailed me the permit and load calcs to show the inspector, along with the install manual and specs for the Blink unit (no operation manual or demonstration was offered during the install, which is OK, since I have already downloaded the manual from the Blink site and figure I can get any help I need on operating it here).

Now I am waiting for the 2nd meter install from SDG&E, which is supposed to happen within 48 hrs. We'll see. We will probably have 1200 miles on the car before it gets its first 240V charge since leaving the dealer. :cry:

TT
Tom Tweed
La Jolla, CA
Plowshare Media
2011 SLe #1317 del. 4/1/11
1st bar lost at 31,953 miles
2nd bar lost at 38,685 miles
3rd bar lost at 50,711 miles
4th bar lost at 59,758 miles after 64 months
Battery replaced at 61,307 miles.

DTB
Posts: 80
Joined: Thu Apr 28, 2011 1:15 pm
Delivery Date: 06 May 2011
Location: West Hills, CA

Re: EV Project/Blink Installs

Thu May 05, 2011 11:29 am

Just had my Blink installed yesterday. When they scheduled the installation the person on the phone said I should expect to pay $500 out of pocket since my panel and garage are on opposite sides of the house. Upon arrival they decided the "best" (ie easiest for them) plan was to run exposed conduit around the outside of the house to the garage. They basically said they'd rather not have to crawl around in the attic or under the house and they might not be able to finish "on time" (which I assume would mean money out of my pocket) but they did leave the decison up to me. I was fine with the exterior conduit since you can't easily see the back/side of my house plus it was free to me.

Here is a look at the installed unit. As others have said, it looks bigger in person.

Image

jcesare
Posts: 583
Joined: Tue Oct 19, 2010 3:22 pm
Delivery Date: 20 Apr 2011
Leaf Number: 1290
Location: San Marcos, CA

Re: EV Project/Blink Installs

Thu May 05, 2011 11:49 am

ttweed wrote:Now I am waiting for the 2nd meter install from SDG&E, which is supposed to happen within 48 hrs. We'll see. We will probably have 1200 miles on the car before it gets its first 240V charge since leaving the dealer. :cry:
TT
FYI The notfication of SDG&E is done by the inspector's office. There was a small snafu in the first install in San Marcos because the inspector didn't realize this. They were very apologetic and have been on top of things since. My meter was installed 2 days after the inspection.

BTW I spent a half hour entering my TOU rates from the Blink touchscreen, then I found out I could have done it from the website. Website is much quicker.
Leaf eTec Blue Ocean
Reserved 6/25/10
EVProject approved 1/06/11
Blink EVSE Installed 4/6/11 (Separate meter, ethernet connection)
Ordered 1/25/11 Delivered 4/20/2011